Jun 28, 2019 Leave a message

Thailand's First Carport Roof Photovoltaic Project Started In Full Swing

Recently, Hubei Engineering Company Design Institute Thailand's car shed photovoltaic project started construction. From May 16th to May 29th, the construction of the car shed photovoltaic project in Thailand was completed within 2 weeks, and the 230-meter safety fence was completed. The general contract personnel of the project department were in place, and the Jianan sub-contractors and machinery were in place. On May 30, the F area was fully started, and the basic floor cutting and cleaning of the current three-fifth area of the F area was completed in five days.

The car shed photovoltaic project is the first car roof photovoltaic project in Thailand. It is the largest single carport photovoltaic project in Southeast Asia. On April 24, 2019, it officially signed an EPC contract with the owner Tenghui Power (Thailand) Co., Ltd. The project has a tight construction period. Due to the complicated customs clearance reporting procedures in the bonded area, the design adopts European and American standards, and the design tasks are concentrated and heavy. The procurement includes local and local purchases in Thailand, all of which are completed by the company itself.

In order to ensure that the first milestone node “completes all construction safety work in Area F on July 15th”, with the strong support of the company's leaders and various departments, the project design, procurement and construction have been fully launched. The design and procurement of the automotive shed PV project is very concentrated, basically concentrated within one month after the contract is signed. At the same time, there are a lot of details in the design and procurement work, and it is necessary to continuously communicate with the owner. The communication work often lasts until 12 pm.

In summer, the average outdoor temperature in Thailand is 35°C, the temperature on the floor reaches 40°C, and now it is also the rainy season. The sweat is always in the work. In the face of the owner's requirements for the "7.15" node, the project department insisted on opening "Dailymeeting" with the owner every afternoon, and summing up the meeting every night with the subcontracting, tracking the progress and nodes according to the days. After continuous combing and efforts, the current project progress meets the requirements of the project and the owner.

Although the current progress meets the requirements, the latter tasks are even more “a long way to go”. The project safety construction, the approval of drawings, the arrival of materials on time and the construction of Jian’an are completed on time, each of which is a heavy task, each task. All need to be carefully planned and constantly tracked. During the Dragon Boat Festival, every employee on the scene misses their loved ones during the festive season. The family's WeChat and video calls are also more, but the "Catch the Way" is insisting.

The car shed PV project in Thailand is crucial to the company's ability to consolidate the Thai PV market and PV EPC compliance. Every step is to go further. Building a beautiful and atmospheric photovoltaic carport and establishing a good corporate image is the goal of the project's electric construction personnel.


Send Inquiry

whatsapp

skype

E-mail

Inquiry